Project Management Orientation
Incorrect. Please try again.
9. What are typical follow-up actions to change requests?
Prepare a schedule to incorporate the change if the change is accepted
Require additional analysis if the change is rejected
Prepare a proposal if the change is deferred
All of the above
SUBMIT
1: Getting Started
2: Define the Project Team
3: Team Management
4: Identify and Validate Requirements
5: Create Decomposition Structures
6: Risk Management
7: Project Estimates
8: Project Schedules
9: Change Management
10: Project Control and Execution
11: Project Management Review
12: Project Closeout
13: Project Management Tool Suite
14: Self-Assessment and Final Exam
Fast Points
Concepts
Seven Keys
Case Study
WWPMM
Mentor
Check Point